Clinton Street – CLOSED TO THROUGH TRAFFIC, DAYTIME – June 18th – July 20th

truck

This will give time to,
1.    Reclaim Street, remove curb and sidewalk - 
2.    DPW install drainage structures and piping -
3.    Water Department to do water connections -
4.    Gas company to install new line -
5.    Repave, Replace curb, prepare sidewalk